Short answer: A driver's home Level 2 install costs $749–$2,500 (Qmerit, national, not city-specific), and TN residential power averages 13.42¢/kWh (EIA, August 2026). Monthly reimbursement = miles × kWh/mile × $0.1342.
Last updated:
What does the home charger install cost?
| Installed range (national) | $749–$2,500 |
|---|---|
| Nashville permit | Electrical permit minimum fee $75 per permit (Metro Code 16.20.250); 220V receptacle $9 each, below minimum. A 10% codes technology fee may apply. |
Sources: Qmerit – How much does Level 2 EV charger installation cost? (national, accessed 2026-10-25); Metro Nashville Codes fee schedule, Metro Code 16.20.250 (official) (accessed 2026-10-25).
How much should we reimburse each month?
Enter miles and the vehicle's kWh per mile (from its window sticker or fleet data).
| TN residential rate | 13.42¢/kWh |
|---|---|
| Formula | miles × kWh/mile × 13.42 ÷ 100 |
Source: EIA Electric Power Monthly, Table 5.6.A (residential, August 2026, preliminary; released Oct 23, 2026) (accessed 2026-10-25). This is a state average. A driver's actual utility tariff may differ.
Is the install cost specific to Nashville?
No. It is Qmerit's national range. The permit line is city-specific where sourced.
Why use the state average rate?
It is the most local residential rate we can source for every city (EIA Table 5.6.A). For exact figures, use the driver's own utility bill.